Construction Update for the week of June 29th, 2009
Last week we were able to see masonry work being done on the extension of the lobby area out toward the corner of Weber Road and High Street (see photo above). What you may not have been able to see, is that steel workers were on site and removing some of the old beams and will be replacing them with new steel decking over the next two weeks. At that time the new flooring will be poured ... here's the part we've all been waiting for...and framing should begin in 3-4 weeks.